  • Schedule

    v4 v5  
    2525|| '''Application'''|| '''1''' || '''2'''  || '''3''' || '''4''' || '''5''' ||
    2626|| [wiki:Changes/atlod atlod]      || 28 || 10 || 20 || || ||
    27 || [wiki:Changes/uvsplit uvsplit]  || 5 || || || || ||
    28 || [wiki:Changes/gpcal gpcal]      ||   || || || 20 || ||
    2927|| [wiki:Changes/invert  invert]   || 10 || || || 5 || 15 ||
     28|| [wiki:Changes/uvsplit uvsplit]  || || 5 || || || ||
    3029|| [wiki:Changes/bbcal bbcal]      ||   || 8 || || || ||
    3130|| [wiki:Changes/gpcopy gpcopy]    || || 8 || || || ||
    3231|| [wiki:Changes/uvacflag uvacflag]|| || || 5 || || ||
    3332|| [wiki:Changes/uvflag uvflag]    ||  || || 10 || || ||
     33|| [wiki:Changes/gpcal gpcal]      ||   || || || 20 || ||
    3434|| [wiki:Changes/mfcal mfcal]      || || || || 20 || ||
    3535|| [wiki:Changes/uvdat uvdat]      ||  || || || 15 || ||
     
    3838|| [wiki:Changes/algorithms new imaging]  ||  || || || || 30 + 15x ||
    3939|| [wiki:Changes/polarization new pol'n] || || || || || ? ||
    40 || '''Totals''' || 45 || 26 || 35 || 60 || 80 + 15x ||
     40|| '''Totals''' || 38 || 31 || 35 || 60 || 80 + 15x ||
    4141----
    4242|| '''Date''' || '''CABB/rx''' || '''miriad''' || '''M'stone''' ||
     
    4444|| Aug-Oct || || Make atlod changes || ||
    4545|| Oct 2007 || CABB stage 1 || Begin test, verify loading || ||
    46 || Nov || || Make gpcal, uvsplit changes || ||
    47 || Dec-Mar || || Make invert changes. Test & verify to end Stage 1. || 6 ||
    48 || Apr 2008 || ATCA shutdown starts  || miriad (Stage 1) available for commissioning tests. || ||
    49 || Jul 2008 || Commissioning complete || miriad Stage 1 needed for astronomy. miriad Stage 2 available (shared-risk). || 8 ||
    50 || Dec 2008 || || miriad Stage 3 released || 9 ||
     46|| Nov-Mar || || Make invert changes. Test & verify to end Stage 1. || 6 ||
     47|| Apr 2008 || ATCA shutdown starts  || Stage 1 available for commissioning tests. || ||
     48|| Jul 2008 || Commissioning complete || Release:stage 1.   Stage 2 available (shared-risk) || 8 ||
     49|| Sep 2008 || || Release:stage 2 ||
     50|| Dec 2008 || || Release:stage 3 || 9 ||
    5151|| Mar 2009 || 1-3 GHz receivers complete  || Very wide fractional bandwidths possible || ||
    5252|| Jun 2009 || 4-12 GHz receivers complete || || ||
    53 || Jun 2009 ||  || miriad stage 4 released || 10 ||
     53|| Jun 2009 ||  || Release:stage 4 || 10 ||
    5454
    5555[/trac/miriad4cabb Wiki Home]