wiki:Schedule

Schedule

Expected timing of relevant events

Event Date Implications
CABB stage 1 2007 Oct-Nov Two element interferometer equipped; CABB data available
Interim CABB installed 2008 May 5 ant, 1 freq in parallel with old system
Commissioning, shared risk observing 2008 Jun - Sep miriad Stage 1,2 needed for CABB data.
ATCA shutdown 2008 October Old system removed; full CABB installed
Science commissioning 2008 December onwards
1-3 GHz receivers complete 2009 ? Very wide fractional bandwidths possible
4-12 GHz receivers complete 2009 ?

The above estimates were entered on 7 Mar 2008.

Previous timetable.

Event Date Implications
CABB stage 1 2007 Oct-Nov Two element interferometer equipped; CABB data available
ATCA shutdown starts 2008 Apr or later
Commissioning complete 2008 Jul or later miriad Stage 1 needed for astronomy.
1-3 GHz receivers complete 2009 Mar Very wide fractional bandwidths possible
4-12 GHz receivers complete 2009 Jun

The above estimates were provided on 17 Aug 2007.

See also: the

Project Stages

Stage Description
1 Basic handling of CABB data. Strong frequency dependencies ignored.
2 Strong frequency dependency handled using the 'divide and conquer' approach; that is, split up the 2 GHz CABB band into a number of sub-bands for which the existing calibration tasks are adequate. Continuum images will be sums of deconvolved images from the sub-bands, limiting the image quality.
3 Use of wide "continuum" bands to calibrate zoom bands.
4 Data flagging on the basis of autocorrelations; single dish analysis modes. Broad bands and data volume is expected to make automatic flagging highly desirable, or essential.
5 Wide bands handled explicitly: calibration and imaging tasks become frequency dependent, removing the limitations imposed by the technique used in stage 2.
6 New algorithms for high-dynamic range imaging and polarimetry

Read ExplanationOfStages for more detail on what each stage will achieve.

Time (days) required for miriad changes for each stage.

Application 1 2 3 4 5 6 Note
atlod 28 10 20
invert 10 5 15
uvsplit 5
bbcal 8 new 'bookkeeping' routine
gpcopy 8
uvacflag 5 new routine. decided not to proceed.
uvflag 10
gpcal 20
mfcal 20
uvdat 15
uvmodel 20
mfclean 15
new imaging 30 + 15x
new pol'n ?
Totals 38 23 8 35 60 80 + 15x

Date CABB/rx miriad M'stone
Aug Complete plan. Fork code into Trac. 1,2,3,4,5
Aug-Oct Make atlod changes
Oct 2007 CABB stage 1 Begin test, verify loading
Nov-Mar Make invert changes. Test & verify to end Stage 1. 6
Apr 2008 ATCA shutdown starts Stage 1 available for commissioning tests.
Jul 2008 Commissioning complete Release:stage 1. Stage 2 available (shared-risk) 8
Sep 2008 Release:stage 2 & 3
Dec 2008 Release:stage 4 9
Mar 2009 1-3 GHz receivers complete Very wide fractional bandwidths possible
Jun 2009 4-12 GHz receivers complete
Jun 2009 Release:stage 5 10