Expected timing of relevant events

Event Date Implications
CABB stage 1 Oct-Nov 2007 Two element interferometer equipped; CABB data available
ATCA shutdown starts not before Apr 2008
Commissioning complete not before July 2008 miriad Stage 1 needed for astronomy.
1-3 GHz receivers complete Mar 2009 Very wide fractional bandwidths possible
4-12 GHz receivers complete June 2009

The above estimates were provided on 17 Aug 2007.

Stage Description
1 Basic handling of CABB data. Strong frequency dependencies ignored.
2 Use of wide "continuum" bands to calibrate zoom bands. Strong frequency dependency handled using the 'divide and conquer' approach; that is, split up the 2 GHz CABB band into a number of sub-bands for which the existing calibration tasks are adequate. Continuum images will be sums of deconvolved images from the sub-bands, limiting the image quality.
3 Data flagging on the basis of autocorrelations; single dish analysis modes. Broad bands and data volume is expected to make automatic flagging highly desirable, or essential.
4 Wide bands handled explicitly: calibration and imaging tasks become frequency dependent, removing the limitations imposed by the technique used in stage 2.
5 New algorithms for high-dynamic range imaging and polarimetry

Time (days) required for miriad changes for to each stage.

Application 1 2 3 4 5
atlod 28 10 20
uvsplit 5
gpcal 20
invert 10 5 15
bbcal 8
gpcopy 8
uvacflag 5
uvflag 10
mfcal 20
uvdat 15
uvmodel 20
mfclean 15
new imaging 30 + 15x
new pol'n ?
Totals 45 26 35 60 80 + 15x

Date CABB/rx miriad M'stone
Aug Complete plan. Fork code into Trac. 1,2,3,4,5
Aug-Oct Make atlod changes
Oct 2007 CABB stage 1 Begin test, verify loading
Nov Make gpcal, uvsplit changes
Dec-Mar Make invert changes. Test & verify to end Stage 1. 6
Apr 2008 ATCA shutdown starts miriad (Stage 1) available for commissioning tests.
Jul 2008 Commissioning complete miriad Stage 1 needed for astronomy. miriad Stage 2 available (shared-risk). 8
Dec 2008 miriad Stage 3 released 9
Mar 2009 1-3 GHz receivers complete Very wide fractional bandwidths possible
Jun 2009 4-12 GHz receivers complete
Jun 2009 miriad stage 4 released 10