= Schedule = == Expected timing of relevant events == || '''Event''' || '''Date''' || '''Implications''' || || CABB stage 1 || 2007 Oct-Nov || Two element interferometer equipped; CABB data available || || Interim CABB installed || 2008 May || 5 ant, 1 freq in parallel with old system || || Commissioning, shared risk observing || 2008 Jun - Sep || miriad Stage 1,2 needed for CABB data. || || ATCA shutdown || 2008 October || Old system removed; full CABB installed || || Science commissioning || 2008 December onwards || || || 1-3 GHz receivers complete || 2009 ? || Very wide fractional bandwidths possible || || 4-12 GHz receivers complete || 2009 ? || || The above estimates were entered on 7 Mar 2008. Previous timetable. || '''Event''' || '''Date''' || '''Implications''' || || CABB stage 1 || 2007 Oct-Nov || Two element interferometer equipped; CABB data available || || ATCA shutdown starts || 2008 Apr or later || || || Commissioning complete || 2008 Jul or later || miriad Stage 1 needed for astronomy. || || 1-3 GHz receivers complete || 2009 Mar || Very wide fractional bandwidths possible || || 4-12 GHz receivers complete || 2009 Jun || || The above estimates were provided on 17 Aug 2007. See also: the [milestone: Roadmap] == Project Stages == || '''Stage''' || '''Description''' || || 1 || Basic handling of CABB data. Strong frequency dependencies ignored.|| || 2 || Strong frequency dependency handled using the 'divide and conquer' approach; that is, split up the 2 GHz CABB band into a number of sub-bands for which the existing calibration tasks are adequate. Continuum images will be sums of deconvolved images from the sub-bands, limiting the image quality. || || 3 || Use of wide "continuum" bands to calibrate zoom bands. || || 4 || Data flagging on the basis of autocorrelations; single dish analysis modes. Broad bands and data volume is expected to make automatic flagging highly desirable, or essential. || || 5 || Wide bands handled explicitly: calibration and imaging tasks become frequency dependent, removing the limitations imposed by the technique used in stage 2.|| || 6 || New algorithms for high-dynamic range imaging and polarimetry || Read [wiki:ExplanationOfStages] for more detail on what each stage will achieve. Time (days) required for miriad changes for each stage. || '''Application'''|| '''1''' || '''2''' || '''3''' || '''4''' || '''5''' || '''6''' || Note || || [wiki:Changes/atlod atlod] || 28 || 10 || || 20 || || || || || [wiki:Changes/invert invert] || 10 || || || || 5 || 15 || || || [wiki:Changes/uvsplit uvsplit] || || 5 || || || || || || || ~~[wiki:Changes/bbcal bbcal]~~ || || 8 || || || || || new 'bookkeeping' routine || || ~~[wiki:Changes/gpcopy gpcopy]~~ || || || 8 || || || || || || ~~[wiki:Changes/uvacflag uvacflag]~~|| || || || ~~5~~ || || || new routine. decided not to proceed. || || ~~[wiki:Changes/uvflag uvflag]~~ || || || || 10 || || || || || [wiki:Changes/gpcal gpcal] || || || || || 20 || || || || ~~[wiki:Changes/mfcal mfcal]~~ || || || || || 20 || || || || [wiki:Changes/uvdat uvdat] || || || || || 15 || || || || [wiki:Changes/uvmodel uvmodel] || || || || || || 20 || || || [wiki:Changes/mfclean mfclean] || || || || || || 15 || || || [wiki:Changes/algorithms new imaging] || || || || || || 30 + 15x || || || [wiki:Changes/polarization new pol'n] || || || || || || ? || || || '''Totals''' || 38 || 23 || 8 || 35 || 60 || 80 + 15x || || ---- || '''Date''' || '''CABB/rx''' || '''miriad''' || '''M'stone''' || || Aug || || Complete plan. Fork code into Trac. || 1,2,3,4,5 || || Aug-Oct || || Make atlod changes || || || Oct 2007 || CABB stage 1 || Begin test, verify loading || || || Nov-Mar || || Make invert changes. Test & verify to end Stage 1. || 6 || || Apr 2008 || ATCA shutdown starts || Stage 1 available for commissioning tests. || || || Jul 2008 || Commissioning complete || Release:stage 1. Stage 2 available (shared-risk) || 8 || || Sep 2008 || || Release:stage 2 & 3 || || || Dec 2008 || || Release:stage 4 || 9 || || Mar 2009 || 1-3 GHz receivers complete || Very wide fractional bandwidths possible || || || Jun 2009 || 4-12 GHz receivers complete || || || || Jun 2009 || || Release:stage 5 || 10 || [/trac/miriad4cabb Wiki Home]