Description
Insert the milestones as shown in the project plan. For each milestone create tickets that define pieces of the work needed to reach the milestone.
Change History (3)
comment:1 Changed 17 years ago by
Component: | prog → Tracker |
---|
comment:2 Changed 17 years ago by
Resolution: | → fixed |
---|---|
Status: | new → closed |
comment:3 Changed 17 years ago by
Billable?: | unset |
---|---|
Component: | Tracker → miriad4cabb project |