Changes between Version 8 and Version 9 of Schedule


Ignore:
Timestamp:
09/05/07 11:49:36 (17 years ago)
Author:
VincentMcIntyre
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • Schedule

    v8 v9  
    22
    33|| '''Event''' || '''Date''' || '''Implications''' ||
    4 || CABB stage 1 || Oct-Nov 2007 || Two element interferometer equipped; CABB data available ||
    5 || ATCA shutdown starts || not before Apr 2008 ||  ||
    6 || Commissioning complete || not before July 2008 || miriad Stage 1 needed for astronomy. ||
    7 || 1-3 GHz receivers complete || Mar 2009 || Very wide fractional bandwidths possible ||
    8 || 4-12 GHz receivers complete || June 2009 || ||
     4|| CABB stage 1 || 2007 Oct-Nov || Two element interferometer equipped; CABB data available ||
     5|| ATCA shutdown starts || 2008 Apr or later ||  ||
     6|| Commissioning complete || 2008 Jul or later || miriad Stage 1 needed for astronomy. ||
     7|| 1-3 GHz receivers complete || 2009 Mar || Very wide fractional bandwidths possible ||
     8|| 4-12 GHz receivers complete || 2009 Jun || ||
    99 
    1010The above estimates were provided on 17 Aug 2007.
     
    2020|| 6 || New algorithms for high-dynamic range imaging and polarimetry ||
    2121
    22 
     22Read [wiki:ExplanationOfStages] for more detail on what each stage will achieve
    2323
    2424Time (days) required for miriad changes for to each stage.