    1010The above estimates were provided on 17 Aug 2007.
    1111
     12
     13
     14|| '''Stage''' || '''Description''' ||
     15|| 1 || Basic handling of CABB data. Strong frequency dependencies ignored.||
     16|| 2 || Use of wide "continuum" bands to calibrate zoom bands. Strong frequency dependency handled  using the 'divide and conquer' approach; that is, split up the 2 GHz CABB band into a number of sub-bands for which the existing calibration tasks are adequate. Continuum images will be sums of deconvolved images from the sub-bands, limiting the image quality. ||
     17|| 3 || Data flagging on the basis of autocorrelations; single dish analysis modes. Broad bands and data volume is expected to make automatic flagging highly desirable, or essential. ||
     18|| 4 || Wide bands handled explicitly: calibration and imaging tasks become frequency dependent, removing the limitations imposed by the technique used in stage 2.||
     19|| 5 || New algorithms for high-dynamic range imaging and polarimetry ||
     20
     21
     22
     23Time (days) required for miriad changes for to each stage.
     24
     25|| '''Application'''|| '''1''' || '''2'''  || '''3''' || '''4''' || '''5''' ||
     26|| atlod   || 28 || 10 || 20 || || ||
     27|| uvsplit || 5 || || || || ||
     28|| gpcal   || 2 || || || 20 || ||
     29|| invert  || 10 || || || 5 || 15 ||
     30|| bbcal   ||   || 8 || || || ||
     31|| gpcopy  || || 8 || || || ||
     32|| uvacflag || || || 5 || || ||
     33|| uvflag  ||  || || 10 || || ||
     34|| mfcal   || || || || 20 || ||
     35|| uvdat   ||  || || || 15 || ||
     36|| uvmodel || || || || || 20 ||
     37|| mfclean || || || || || 15 ||
     38|| new imaging ||  || || || || 30 + 15x ||
     39|| new pol'n || || || || || ? ||
     40|| '''Totals''' || 45 || 26 || 35 || 60 || 80 + 15x ||
     41----
     42|| '''Date''' || '''CABB/rx''' || '''miriad''' || '''M'stone''' ||
     43|| Aug || || Complete plan. Fork code into Trac. || 1,2,3,4,5 ||
     44|| Aug-Oct || || Make atlod changes || ||
     45|| Oct 2007 || CABB stage 1 || Begin test, verify loading || ||
     46|| Nov || || Make gpcal, uvsplit changes || ||
     47|| Dec-Mar || || Make invert changes. Test & verify to end Stage 1. || 6 ||
     48|| Apr 2008 || ATCA shutdown starts  || miriad (Stage 1) available for commissioning tests. || ||
     49|| Jul 2008 || Commissioning complete || miriad Stage 1 needed for astronomy. miriad Stage 2 available (shared-risk). || 8 ||
     50|| Dec 2008 || || miriad Stage 3 released || 9 ||
     51|| Mar 2009 || 1-3 GHz receivers complete  || Very wide fractional bandwidths possible || ||
     52|| Jun 2009 || 4-12 GHz receivers complete || || ||
     53|| Jun 2009 ||  || miriad stage 4 released || 10 ||
     54
    1255[/trac/miriad4cabb Wiki Home]