| 12 | |
| 13 | |
| 14 | || '''Stage''' || '''Description''' || |
| 15 | || 1 || Basic handling of CABB data. Strong frequency dependencies ignored.|| |
| 16 | || 2 || Use of wide "continuum" bands to calibrate zoom bands. Strong frequency dependency handled using the 'divide and conquer' approach; that is, split up the 2 GHz CABB band into a number of sub-bands for which the existing calibration tasks are adequate. Continuum images will be sums of deconvolved images from the sub-bands, limiting the image quality. || |
| 17 | || 3 || Data flagging on the basis of autocorrelations; single dish analysis modes. Broad bands and data volume is expected to make automatic flagging highly desirable, or essential. || |
| 18 | || 4 || Wide bands handled explicitly: calibration and imaging tasks become frequency dependent, removing the limitations imposed by the technique used in stage 2.|| |
| 19 | || 5 || New algorithms for high-dynamic range imaging and polarimetry || |
| 20 | |
| 21 | |
| 22 | |
| 23 | Time (days) required for miriad changes for to each stage. |
| 24 | |
| 25 | || '''Application'''|| '''1''' || '''2''' || '''3''' || '''4''' || '''5''' || |
| 26 | || atlod || 28 || 10 || 20 || || || |
| 27 | || uvsplit || 5 || || || || || |
| 28 | || gpcal || 2 || || || 20 || || |
| 29 | || invert || 10 || || || 5 || 15 || |
| 30 | || bbcal || || 8 || || || || |
| 31 | || gpcopy || || 8 || || || || |
| 32 | || uvacflag || || || 5 || || || |
| 33 | || uvflag || || || 10 || || || |
| 34 | || mfcal || || || || 20 || || |
| 35 | || uvdat || || || || 15 || || |
| 36 | || uvmodel || || || || || 20 || |
| 37 | || mfclean || || || || || 15 || |
| 38 | || new imaging || || || || || 30 + 15x || |
| 39 | || new pol'n || || || || || ? || |
| 40 | || '''Totals''' || 45 || 26 || 35 || 60 || 80 + 15x || |
| 41 | ---- |
| 42 | || '''Date''' || '''CABB/rx''' || '''miriad''' || '''M'stone''' || |
| 43 | || Aug || || Complete plan. Fork code into Trac. || 1,2,3,4,5 || |
| 44 | || Aug-Oct || || Make atlod changes || || |
| 45 | || Oct 2007 || CABB stage 1 || Begin test, verify loading || || |
| 46 | || Nov || || Make gpcal, uvsplit changes || || |
| 47 | || Dec-Mar || || Make invert changes. Test & verify to end Stage 1. || 6 || |
| 48 | || Apr 2008 || ATCA shutdown starts || miriad (Stage 1) available for commissioning tests. || || |
| 49 | || Jul 2008 || Commissioning complete || miriad Stage 1 needed for astronomy. miriad Stage 2 available (shared-risk). || 8 || |
| 50 | || Dec 2008 || || miriad Stage 3 released || 9 || |
| 51 | || Mar 2009 || 1-3 GHz receivers complete || Very wide fractional bandwidths possible || || |
| 52 | || Jun 2009 || 4-12 GHz receivers complete || || || |
| 53 | || Jun 2009 || || miriad stage 4 released || 10 || |
| 54 | |