Meetings/20080808
Catchup discussion
Agenda
- test cases
- bbcal design
- cabb update
- PRB result
Minutes
- test cases
- not ready
- bbcal design
- no time to work on it
- cabb update
- no change, still going for 3 antennae. Leach in an accident, holds up sampler construction.
- PRB result
-
- green.
- we need to ask PRB to shift milestones again
- stage 3 needs zoom bands working. This requires all the processing boards to be available.
- move stage 4 to Apr 09.
- split stage 2&3 release milestone.
- stage 2 release in Feb 09
- stage 3 available to test in Feb 09
- when will interim system be available?
- stage 5 - move from April to 4 mo after stage 4 release.
- 1-3 GHz, where largest fractional b/w effects are, pushed out to 2010 October. May not be done?
- cut back on meetings for the next few weeks
Actions
- VM talk to PRB
- VM revise timeline in spreadsheet
- VM redo schedule table in wiki
- VM circulate new status document by email
- VM open tickets for bbcal, test framework
Participants
- Mark
- Dave
- Vince
Last modified 15 years ago