wiki:Meetings/20080808

Meetings/20080808

Catchup discussion

Agenda

test cases
bbcal design
cabb update
PRB result

Minutes

test cases
not ready
bbcal design
no time to work on it
cabb update
no change, still going for 3 antennae. Leach in an accident, holds up sampler construction.
PRB result
  • green.
  • we need to ask PRB to shift milestones again
  • stage 3 needs zoom bands working. This requires all the processing boards to be available.
    • move stage 4 to Apr 09.
    • split stage 2&3 release milestone.
      • stage 2 release in Feb 09
      • stage 3 available to test in Feb 09
  • when will interim system be available?
    • stage 5 - move from April to 4 mo after stage 4 release.
    • 1-3 GHz, where largest fractional b/w effects are, pushed out to 2010 October. May not be done?
  • cut back on meetings for the next few weeks

Actions

  • VM talk to PRB
  • VM revise timeline in spreadsheet
  • VM redo schedule table in wiki
  • VM circulate new status document by email
  • VM open tickets for bbcal, test framework

Participants

  • Mark
  • Dave
  • Vince