  • Meetings/20080509

    v1 v2  
    44
    55== Agenda ==
    6  * status reports?
     6 * status reports.
    77
    88== Minutes ==
     9 * CABB progress status discussed; recent report to ATUC (see https://svn.atnf.csiro.au/trac/atoperations/wiki/CABB/Status_2008-05-07)
     10    * Final CABB installation delayed until late January 2009
     11    * Interim CABB still on track for July 2008: 5 antennas, 1 frequency.
     12 * Mark Wieringa on leave from 27 June - 21 July
     13 * Vince on BETR training 2,3,4 June
     14 * Mark: BETR training 26 May
     15 * Mark, Dave meet in Marsfield for architecture discussions: 27-28 May.
     16 * We see late May until 26 June as a critical period for miriad work.  The first CABB data files will become available (we think) in the latter part of May.  The first observation is scheduled (C1798 Lommen, 3mm) is on 30 June.  The sequence might be:
     17    * get access to trial rpfits file, and test loading into miriad
     18    * discuss with Warwick issues arising on calibration processes such as multi-frequency Tsys measurements and access to them
     19    * development of file generation and miriad to establish an efficient process
     20    * release to early users for testing.
     21 * Mark's time will be precious in that period.  David Brodrick and Euan Troup are on leave at present but return to work week after next. NASA tracking has the potential to demand Mark's time. This should be resisted if possible.
     22 * Vince reported on discussions with Juan-Carlos on code reviews.  Need a code standard to make these worthy of the effort.  Again pointed to site that supports code reviews  [http://www.review-board.org/].
    923
    1024== Participants ==