plan: set milestones

Reported by: VincentMcIntyre Owned by: VincentMcIntyre
Priority: major Milestone: 4. Draft plan complete
Component: miriad4cabb project Version:
Keywords: Cc:
Estimated Number of Hours: Add Hours to Ticket:
Billable?: no Total Hours: 0

Description

Once we know what we have to do, set up the sequence of events and decide where the milestones are - points where there is a visibly completed piece of work.

Change History (2)

comment:1 Changed 17 years ago by VincentMcIntyre

Resolution: fixed
Status: newclosed

comment:2 Changed 17 years ago by VincentMcIntyre

Billable?: unset
Component: Projectmiriad4cabb project