#70 VincentMcIntyre VincentMcIntyre fixed provide tree of compiled 'cabb-version' code.
Description

We need a distinct tree of programs and documentation that have been built from the 'cabb' branch of the RCS repository.

This might be tricky to do owing to the intricacy of the make files.

#35 MarkWieringa MarkWieringa fixed atlod changes to cope with 3mm xy noise cal on a single antenna
Description

A new 3mm receiver with noise calibration source will be installed on the ATCA shortly. Data from 19OCT07 onwards will have valid XY phase and amplitude syscal data. Currently atlod ignores all xy syscal data for 3mm. Correct polarization calibration of the array requires the xy phase on the new antenna to be applied to the y correlation on all baselines.

The first polarization observations requiring this will start on 22OCT07.

#71 VincentMcIntyre VincentMcIntyre fixed PRB report 2009 Feb
Description

We need to send in another progress report.

Your assistance is sort to ensure an informative and efficient Projects Meeting. Please provide all reports to Phil and myself by COB 3rd February 2009

Reports should reflect the position as at the end of December 2008. December 2008 financial data are currently available on SAP. In putting information together it would be helpful to note any anticipated large January expenditure.

All templates are available on the Project Help site

In this report we will have to request changes to the plan, thanks to the hardware delays we are well out of kilter with what we forecast.