Schedule
v14 v15 6 6 || CABB stage 1 || 2007 Oct-Nov || Two element interferometer equipped; CABB data available || 7 7 || Interim CABB installed || 2008 May || 5 ant, 1 freq in parallel with old system || 8 || Commissioning, shared risk observing || 2008 Jun - Sep || miriad Stage 1 needed for CABB data. ||8 || Commissioning, shared risk observing || 2008 Jun - Sep || miriad Stage 1,2 needed for CABB data. || 9 9 || ATCA shutdown || 2008 October || Old system removed; full CABB installed || 10 || Science commissioning || 2008 December onwards || Need miriad stages 2, 3||10 || Science commissioning || 2008 December onwards || || 11 11 || 1-3 GHz receivers complete || 2009 ? || Very wide fractional bandwidths possible || 12 12 || 4-12 GHz receivers complete || 2009 ? || ||