69 | | * Vince & Naomi to discuss CABB commissioning plan with Jim |
| 69 | * Vince & Naomi to discuss CABB commissioning plan with Jim Caswell |
| 70 | |
| 71 | '''Update 2008-06-13'''[[BR]] |
| 72 | It turns out Jim is planning to use real observations as the "commissioning" process. |
| 73 | Most of the tests of the correlator that one would want to do in a formal commissioning period |
| 74 | will already be done by Warwick and co in their test procedures. |
| 75 | |
| 76 | So it appears our task is to look at the schedule and check for tasks that are likely to be needed, |
| 77 | and work on those with higher priority. |